20th Street Reconstruction
We will be working on tie ins on 12/20/2022 to 12/22/2022. Water will be off @ 8:30am on the scheduled day. Sorry for the inconvenience and will be working as quick as possible to restore the service.
12/20/2022 – Alley South of Penasco Apartments (2 tie ins)
12/21/2022 – Alley South of Washington (2 tie ins)
12/22/2022 – Ray Street water line (tie in)
Concrete work will be done between 12/27/2022 and 12/29/2022 so there will be no water interruption.
Tie Ins will resume at the beginning of the year 1/3/2022 to 1/5/2022, water will be off @ 8:30 am until work is completed on the scheduled day.
1/3/2023 – Alley North of Briscoe (tie ins)
1/4/2023 – Alley North of Bullock & Alley North of Mann (tie ins)
1/5/2023 – Mann Street (tie ins)
Please help us keep work crews, motorists, and citizens as safe as possible in these areas. As a reminder when “Road Closed” signs are posted this does not permit any traffic to travel through the construction site. Please also obey posted speed limits. If you have questions, feel free to contact us at 575-748-9821.